Warehouse complex UnitB Gatne village
The construction of the complex was carried out as part of the works of the general contractor. The main task was the construction and commissioning of the facility in 6 months. The execution of works on the construction of concrete roads and improvement of the territory fell on the winter period, in connection with which the works were carried out by the method of heating concrete.
During construction, 250 tons of metal structures were manufactured and assembled, 3800 cubic meters of concrete were poured.
Year
2020
Location
Hatne, Kyiv region
Function
Warehouse complex
Type of activity
New construction
Area
3 200 sq m