Construction Group MODUS was a subcontractor in the construction of the hydro power station and performed a full cycle of construction works:
- installation of monolithic reinforced concrete and metal structures of the water intake and the power house;
- waterproofing works;
- masonry works;
- installation of external facades and roof of the HPS building;
- installation of monolithic structures of the water discharge channel;
- finishing work.
As the construction process was taking place in flooded soils, measures were taken to dewater them and dispose of groundwater. Some work on installation of monolithic reinforced concrete structures was carried out directly in the water.
Year
2014
Location
Donetsk region, Ukraine
Function
Energy object
Type of activity
New construction
Area
8 000 sq м